S-34.1, r. 2 - Regulation respecting petroleum exploration, production and storage on land

Full text
280. The authorization holder who temporarily closes a well must ensure
(1)  that the facilities and equipment installed in the well are compatible with what is planned in the permanent well or reservoir closure and site restoration plan;
(2)  that the facilities and equipment installed in the well are durable and corrosion-resistant;
(3)  the absence of communication of fluids between the geological formations;
(4)  the absence of leaks in joints and welds;
(5)  that the valve on the surface casing vent flow pipe is open and the vent is not blocked;
(6)  to install a hemispherical head plug or a blind flange with a needle valve to read the flow at each outlet of the wellhead, except the surface casing vent flow;
(7)  if applicable, to disconnect the wellhead flow pipe; and
(8)  to chain and lock the valves or remove the handles.
O.C. 1252-2018, s. 280.
In force: 2018-09-20
280. The authorization holder who temporarily closes a well must ensure
(1)  that the facilities and equipment installed in the well are compatible with what is planned in the permanent well or reservoir closure and site restoration plan;
(2)  that the facilities and equipment installed in the well are durable and corrosion-resistant;
(3)  the absence of communication of fluids between the geological formations;
(4)  the absence of leaks in joints and welds;
(5)  that the valve on the surface casing vent flow pipe is open and the vent is not blocked;
(6)  to install a hemispherical head plug or a blind flange with a needle valve to read the flow at each outlet of the wellhead, except the surface casing vent flow;
(7)  if applicable, to disconnect the wellhead flow pipe; and
(8)  to chain and lock the valves or remove the handles.
O.C. 1252-2018, s. 280.